Project: Double Span Bridge Construction in Tehran- Shomal Highway
Employer: Tehran-Shomal highway company
Contract: PC
Start and finish date: 2007-5-27 until 2008-11-27
Discipline:
- Civil
- Mechanical
- Electrical
Highlights:
The Bridge consisted of plate girder on each side, 100,000 kg girders. The bridge was constructed using strand jacks. The jacks were arranged in a "pull-push" configuration enabling accurate and thorough control throughout the installation of the main elements (girders).
|
Items of works: |
|
|
Earth works |
45,000 m3 |
|
Earth fill works |
250,000m3 |
|
Reinforcement |
450,000 kg |
|
Concreting |
4,000m3 |
|
Steel structures |
1,000,000 kg |